Do you need permission from the network operator to fit solar panels?
Published 6 November 2026
Usually not, but the network operator always has to be told. A home system whose inverters add up to no more than 16 amps per phase (3.68kW on an ordinary single-phase supply) falls under the rules known as G98: it can be fitted and switched on first, and the network operator notified within 28 days. A bigger system, including many solar-and-battery systems, falls under G99 and needs the network operator's approval before it is fitted. In both cases the installer normally sends the paperwork, but it is worth checking that they have.
Who the network operator is
The network operator (often called the DNO, distribution network operator) runs the cables and substations in your area. It isn't the company you pay your bills to. You can find yours by postcode on the Energy Networks Association's Who's my network operator? page. MCS, the body that certifies installers, says you can also match the first two digits of your MPAN, the number on your electricity bill, to the operator list (MCS, Notifying DNOs).
Which route applies
| Your system | Route | When the network operator hears |
|---|---|---|
| Type-tested inverters totalling 16A per phase or less (3.68kW single-phase) | G98 | After you switch on: paperwork within 28 days of commissioning |
| More than 16A per phase, or equipment that isn't type-tested | G99 | Before fitting: apply and wait for approval |
| Solar and battery together above 16A per phase, type-tested, with export limited | G99 fast track | Before fitting, through a shorter application |
MCS's guidance says notification "is required in all cases" for solar panels, that G98 systems are notified within 28 days of commissioning, and that systems over 16A per phase need prior permission under G99 (MCS, Notifying DNOs).
What counts towards the 16A limit
The limit is for everything at your home, not for each new item. National Grid Electricity Distribution, one of the network operators, says G98 applies where the "aggregate registered capacity" is 16A (3.68kW) per phase or less, adding up every unit at the premises at its AC rating, whether or not they ever run at full output together. For solar panels, that rating is the inverter's continuous rating, not the panels' total (National Grid, G98 connection procedures). So a 4kW array on a 3.68kW inverter can still be G98, while adding a second inverter or a battery inverter later can tip the home over the limit.
Batteries count. MCS says network operators treat a battery as demand when it charges from the grid and as generation when it exports, and that a solar-and-battery system will usually come to more than 16A per phase, so G99 applies (MCS). National Grid's fast-track rules count "generation / storage devices" together towards the same limits (National Grid, G99 fast track).
The G99 fast track for solar and batteries
Network operators have a quicker G99 route for homes adding type-tested solar and battery equipment above 16A per phase. National Grid's version, for example, covers:
- devices of up to 16A each totalling up to 32A per phase, with export to the grid limited to 16A by a G100 export limitation scheme; and
- devices of up to 32A each totalling up to 60A per phase, with export limited to 32A.
All the equipment has to be fully type-tested and fitted at an existing home, and National Grid says it will reply within 10 working days (National Grid, G99 fast track). A home with a single 16A-or-less system that already meets G98 simply notifies. Other network operators set out their own fast-track limits, so check your operator's page.
More than one home at once
If systems are going on several homes close together, such as a terrace or a new estate, G98 is no longer fit-then-tell. National Grid's rules say that if other G98 equipment has been or will be connected within 500 metres within 28 days, the installer applies first on a multiple-installations form and must have the details agreed before switching on (National Grid, G98 connection procedures).
Northern Ireland
NIE Networks uses its own versions, G98/NI and G99/NI, with the same 16A-per-phase line between them; it gives 16A as 3.68kVA single-phase or 11.04kW three-phase, and charges no application fee for G98/NI. Since 1 May 2026 its G99/NI fast track covers up to 60A per phase, with each inverter up to 32A and export still limited to 16A per phase. NIE Networks says the fast track "is not a 'Fit and Inform' process": approval must come before installation starts (NIE Networks, G99/NI Fast Track).
What to ask your installer
- Is the system G98, G99 fast track or full G99, and what is the total inverter rating, including any battery?
- If it is G99, has the network operator approved it? Don't book the fitting until it has.
- If it is G98, will they send the notification within 28 days of commissioning, and can you have a copy?
- Are the inverters listed as type-tested? Both National Grid's G98 rules and its fast track depend on it.
An MCS-certified installer is expected to do the notifying (MCS). Network operators can ask for their own forms, so the details differ between areas. This page is separate from planning permission and building regulations, which have their own rules.
Sources
- MCS, Notifying DNOs.
- National Grid Electricity Distribution, G98 connection procedures.
- National Grid Electricity Distribution, G99 connection procedures.
- National Grid Electricity Distribution, Generation (G99) fast track.
- NIE Networks, G99/NI Fast Track installations.
- Energy Networks Association, Who's my network operator?
Checked on 5 November 2026.