Do you need planning permission for a home EV charger?
Published 6 November 2026
Usually not, in England. A wall-mounted charger or a small charging post on your driveway, garage or other off-street parking space counts as permitted development, so you don't need to apply. Since 21 October 2026 that also covers a charger elsewhere on your property, such as the front wall of a house with no driveway, as long as the cable crosses any pavement through a channel the council has authorised. You do need planning permission if your home is a listed building or a scheduled monument, if the charger breaks the size or height limits below, or if your council has removed these rights in your area. These rules were checked against the law on legislation.gov.uk on 6 November 2026.
What changed on 21 October 2026
The Town and Country Planning (General Permitted Development) (England) (Amendment) (No. 2) Order 2026 came into force on 21 October 2026. Before then, a home charger was only permitted development within an area lawfully used for off-street parking. The order extends this to any other part of the curtilage of a house or block of flats (the land that goes with the building), adds new limits for those chargers, and lets councils fit cross-pavement cable channels without planning permission. The government announced it as saving drivers up to £300 on installation.
If something you planned was permitted under the old rules but isn't under the new ones, the order lets you carry it out under the old rules until the end of 20 October 2027.
The limits for a home charger
The rules are in Class D (wall-mounted chargers) and Class E (chargers on a post, called an upstand) of Part 2 of Schedule 2 to the General Permitted Development Order. A charger is permitted development only if it stays within all of these.
| Rule | Wall-mounted charger | Charger on a post |
|---|---|---|
| Size | No more than 0.2 cubic metres, including its casing | No volume limit in the law |
| Height | Not more than 1.6 metres above the ground | No more than 1.6 metres high at a home |
| How many | One, if it isn't in a parking area | One per parking space |
| Conservation area | Allowed in an off-street parking area; not allowed elsewhere on the property | Allowed in an off-street parking area; not allowed elsewhere on the property |
| Listed building or scheduled monument | Not allowed anywhere within its curtilage | Not allowed anywhere within its curtilage |
| Wall next to a pavement | Sticks out no more than 0.2 metres, and leaves at least 1.5 metres of pavement to the edge of the road | Not applicable |
A standard three-pin socket isn't covered by these rules: the law defines a charger as a dedicated charging point, not a domestic plug and socket. When you no longer need the charger for charging, you must remove it as soon as reasonably practicable and put the wall or ground back as it was.
If you park on the street
A charger on your own wall or front garden is now permitted development even with no driveway, but only on one condition: where there is a pavement between the charger and the car, the cable must cross it through an authorised cross-pavement solution while you're charging. The law defines that as a cable channel set into the pavement, installed by, on behalf of, or with the authorisation of the highway authority, which is usually your council. A cable laid across the pavement, even under a mat or cover, isn't a channel set into the pavement, so it doesn't meet the condition.
The council's own work fitting the channel is permitted development under a new Class F of Part 9, except in a conservation area, within the curtilage of a listed building, or on a scheduled monument. The Planning Portal's summary points out that this doesn't let residents put in a channel themselves, and that the council's approval and any street works permissions are still needed separately. So if you have no driveway, ask your council first whether it will authorise a channel outside your home, what it charges and how long it takes. The government grant for households with on-street parking also depends on having one.
When you need to apply
Where permitted development doesn't cover your charger, you need to apply to your council for planning permission, normally householder planning permission, says the Planning Portal. That includes:
- a home that is a listed building, or a charger anywhere within a listed building's curtilage;
- a charger outside your parking area in a conservation area;
- a charger bigger or taller than the limits above, or more than one post per parking space;
- an area where the council has taken away permitted development rights, for example with an Article 4 direction.
If you're not sure whether your home is listed, in a conservation area or under an Article 4 direction, your council's planning department can tell you.
Building regulations still apply
Planning permission is a separate question from building regulations. The Planning Portal's building regulations guide says installing a home charger is notifiable work, which must be reported to your local building control body unless it's done by an electrician registered with a competent person scheme. Most installers are registered and deal with this for you; ask yours to confirm.
Wales, Scotland and Northern Ireland
The rules on this page are England's. Wales, Scotland and Northern Ireland each set their own permitted development rights, and the 21 October 2026 changes don't apply there. Wales added rights for chargers in off-street parking areas in its 2019 amendment order, and Scotland's are explained in the Scottish Government's planning circular 2/2024. If you live outside England, check with your council before you have a charger fitted.
Sources
- The Town and Country Planning (General Permitted Development) (England) (Amendment) (No. 2) Order 2026
- General Permitted Development Order 2015, Schedule 2, Part 2, Class D
- General Permitted Development Order 2015, Schedule 2, Part 2, Class E
- GOV.UK: Drivers to save up to £300 when installing EV chargers at home