Can you install a home EV charger yourself?
Published 14 November 2026
In England, the law doesn't require a professional, but it does require the work to be certified, and you can't certify it yourself. Fitting a home charger means a new circuit, which is notifiable work under the building regulations. If you aren't a registered electrician, you must either tell your council's building control (or a private building control approver) before you start, and let it inspect the work, or appoint a registered third-party certifier before you start. Doing it yourself also rules out the government's chargepoint grant, which only pays through an authorised installer. Wales, Scotland and Northern Ireland have their own rules. This page was checked against the regulations and GOV.UK on 13 November 2026, and it describes the rules rather than whether you have the skills: if you aren't a qualified electrician, use one.
Why a charger counts as notifiable work
Part P of the Building Regulations 2010 covers electrical safety in homes, and regulation 12(6A) makes three kinds of electrical work notifiable in England: installing a new circuit, replacing a consumer unit, and adding to or altering circuits in the space around a bath or shower. The Planning Portal's building regulations guide for EV chargers says building regulations approval is always needed for a home charger, because it involves a new circuit. It also says it's up to the householder, not the installer, to make sure the right approvals are in place.
The three ways to get the work certified
Approved Document P, the government's guidance on Part P, sets out three routes (paragraph 3.1):
| Who does the work | How it's certified | When you must act |
|---|---|---|
| An electrician registered with a competent person scheme | They self-certify, and their scheme sends a compliance certificate to you and building control within 30 days | Nothing for you to file |
| Anyone else, using a registered third-party certifier | The certifier inspects and tests the work, and its registration body sends the certificate within 30 days | Appoint the certifier before work begins, and tell it within 5 days of finishing |
| Anyone else, using building control | The building control body decides what inspection and testing it needs, then issues a completion or final certificate | Notify building control before work begins |
For the third-party route, schedule 3A to the regulations names one body for electrical work in homes in England: people registered for it by NAPIT Registration Limited. For the building control route, the Planning Portal says you can notify with a building notice or a full plans application, and that work can start two days after the notice goes in. Councils set their own fees, and Approved Document P (paragraphs 3.10 and 3.11) says a council can charge less if you're competent to test the work yourself and give it the BS 7671 certificate.
Whichever route you use, Approved Document P says the work should be designed, installed, inspected and tested to BS 7671, the national wiring regulations.
What you lose by doing it yourself
- The grant. If you rent, own a flat or park on the street, the government pays 75% of the cost, up to £500. The terms of both the grant for renters and flat owners and the grant for households with on-street parking say you must use an OZEV-authorised installer and an eligible chargepoint, and the installer claims the grant and takes it off your invoice. There's no route for a self-installed charger. If you own a house with a driveway, there's no grant to lose.
- The network operator notification. Your electricity network operator has to be told about a new charger, and some homes need its approval first. SSEN's guidance, for example, expects the installer to send the notification, within 28 days of installation, and to apply before fitting if the home's total demand would go over 60 amps. If you fit it yourself, ask your network operator how it wants to be told.
- The paperwork when you sell. GOV.UK warns that without approval you won't have the certificates you may need when you sell your home.
The charger's warranty and your home insurance may also depend on who fitted it; check the manufacturer's terms and your policy before you start.
If you skip the certification
GOV.UK says the person doing the work could be prosecuted and fined for not complying with the building regulations, and that building control could make you pay to fix faulty work. Approved Document P (paragraph 3.14) adds that councils can take enforcement action over unsafe electrical work even where it isn't notifiable. If a charger is already in and you don't know whether it was certified, the Planning Portal suggests asking your council's building control, or the registered electrician who fitted it.
Wales, Scotland and Northern Ireland
- Wales also has Part P, but regulation 12(6A), which sets England's list of notifiable electrical work, doesn't apply there, so the list of notifiable work isn't the same as England's. Ask your council's building control before you start.
- Scotland uses building warrants instead. The local authority verifiers' information paper INFOP25 (February 2020) says a charger that draws its supply from a building is treated as a new power socket outlet, so whether you need a warrant depends on the type and height of the building. A charger not supplied from or attached to a building needs no warrant. Your council's building standards team can confirm.
- Northern Ireland has its own building regulations. Check with your council's building control.
Sources
- legislation.gov.uk: The Building Regulations 2010, regulation 12 and schedule 3A
- GOV.UK: Approved Document P, Electrical safety: dwellings (2013 edition)
- Planning Portal: Electric vehicle charging, building regulations
- GOV.UK: Building regulations approval, when you need approval
- Find a grant: EV chargepoint grant for renters and flat owners
- Find a grant: EV chargepoint grant for households with on-street parking
- SSEN: Charging at home
- Local Authority Building Standards Scotland: INFOP25, installation of electric vehicle charging points