Do you need to tell your network operator about a home EV charger?

Published 13 November 2026

Yes, but your installer does it, not you. In Great Britain, if your home's supply can take the extra load, a single charger can be fitted first and the installer then notifies the local distribution network operator (DNO), the company that runs the cables to your home. SSEN, for example, asks for that notification within 28 days of installation. The installer has to apply and wait for approval before fitting it if your home's total demand would go over 60 amps, or if your supply is looped, meaning it shares a service cable with a neighbour. In Northern Ireland, NIE Networks says every application must be made before installation. These rules were checked on SSEN's, National Grid's, NIE Networks' and Ofgem's own sites on 12 November 2026.

Notify after, or apply before

There are two routes, often called "connect and notify" and "apply to connect". SSEN's guidance on charging at home sets them out plainly:

Your homeRouteWhen the network operator hears
Total demand 60 amps or less, and no safety concernsConnect and notifyAfter the charger is fitted, within 28 days
Total demand over 60 amps, or it doesn't meet the other criteriaApply to connect (SSEN calls it a load check)Before installation; the installer waits for approval
Looped supply, shared with another propertyApply to connectBefore installation, so SSEN can decide whether to unloop it

"Total demand" means the most your whole home could draw at once with the charger added, which your installer works out from what you already have, such as an electric shower, cooker or heat pump. A typical 7kW home charger draws about 32 amps on its own, which is why it can tip a busy home over 60 amps. SSEN takes notifications through its website, by email on the standard industry (ENA) form, or through the Connect Direct portal.

Other network operators run the same two routes, but their criteria and deadlines can differ in detail, so the installer checks the rules of the operator for your area. National Grid Electricity Distribution, for example, has one online form both to apply for a new charger and to notify it of one already installed, and says you will hear back within 10 working days with the next steps.

Who does it

The installer. SSEN's page puts the job on the installer, and National Grid says the wiring and installation must be done by a qualified electrician. In practice, ask your installer before you book whether your home is a "notify" or an "apply" job, and to confirm once the notification has gone in. If the installer says the supply needs work first, expect a wait while the network operator looks at it.

Northern Ireland is different

NIE Networks' answers on low carbon technologies say all applications must be made before installation. Your installer applies online, and NIE Networks either approves it or arranges a visit to assess the property. It says most installations at existing homes don't need any work from it, but gives no fixed time for a reply, because each one is assessed individually.

Who pays if your supply needs an upgrade

If your main fuse, the cable into your home or a looped supply has to be changed before the charger can be used safely, the network operator arranges it. National Grid says it may need to do some work after a charger is fitted, such as a fuse upgrade, and SSEN says it will arrange any upgrade or unlooping before installation where the supply can't take the extra demand.

Neither SSEN's nor National Grid's page mentions a fee for notifying. On the cost of any work, Ofgem changed the rules in Great Britain from 1 April 2023: in its final decision on access and connection charges, published on 3 May 2022, it removed the contribution that people adding demand used to pay towards reinforcing the shared network, so a connecting customer pays only for "extension assets", the new equipment that serves them alone. Whether a particular job falls into that is for the network operator, so if it quotes you a charge, ask it to explain what the charge is for before you agree.

What to do

The network operator isn't your energy supplier, and your installer will know which one covers your area.