Do you have a legal right to decent broadband?

Published 11 November 2026

Yes, if your home or business can't get a decent, affordable connection now. Under the broadband universal service obligation you can ask BT (or KCOM, if you're in the Hull area) to provide one, and it must do so where the work costs no more than £3,400. "Decent" means at least 10Mbps download and 1Mbps upload, set in the law that created the right. If the work costs more, you can still have it, but you pay the part above £3,400. It isn't a right to full fibre or to a particular technology, and you don't qualify if a public scheme will reach you within a year or, BT says, if you can already get a qualifying 4G service. The details below are from the law and from BT's and KCOM's own pages as they stood on 10 November 2026.

What counts as decent broadband

The Electronic Communications (Universal Service) (Broadband) Order 2018 sets the minimum. The connection must give you:

The Order doesn't say which technology has to deliver it, so a new fixed line isn't guaranteed. BT's USO page says you can only ask for a build if you can't get a connection through a 4G hub in your region.

Who qualifies

Under the Order, the right applies to a fixed location that is a home or a place of business, where you ask for the connection and:

The service also has to be affordable. BT's USO page says Ofcom defines affordable as no more than £59.60 a month, so if the only decent service you can get costs more than that, you can still ask. KCOM's USO page gives £57.60 a month, including VAT, and says the figure is adjusted with inflation (CPI). The two pages may have been updated at different times, so check the current figure with whichever provider covers you.

What you pay if it costs more than £3,400

The £3,400 is the cost of building the connection, not your monthly bill. BT says the limit excludes VAT, and if the build costs more, you pay the difference for the work to go ahead.

BT also says that where several eligible homes in an area can be connected by the same build, the extra cost is shared between them:

KCOM says that above £3,400 you can pay the excess or do some of the work yourself.

How to ask, and how long it takes

Outside Hull: request a universal service connection through BT's help desk, from its USO page. BT says it will then:

  1. confirm whether your address is eligible and whether the estimated cost is under £3,400, which may take 30 days
  2. if the estimate is over £3,400, survey the route and give you a final quote, which may take 60 days
  3. start planning once you've paid any excess. You have 30 days to change your mind, after which the payment isn't refundable except under BT's universal service terms

BT aims to finish builds within 12 months, but says some take up to 24 months and exceptional ones longer, because of things like road closure permits, obstacles on the cable route, archaeology or protected wildlife. It says it will tell you if your build will take more than 24 months or can't be done.

In the Hull area: call KCOM on 01482 602555, or enter your postcode on its USO page. KCOM says it has up to 30 days to confirm you're eligible, and if the estimate is over £3,400 and you want to go ahead, a detailed quote follows within 60 days.

Before you ask